
Sway Bracing Layout
Earthquake Resistant Fire Protection System
Over the past few months the havoc
that earthquakes can wreak has been
abundantly clear. While the devastation in
Haiti wrought by substandard building
codes is not likely to be repeated soon, fire
protection systems can be vulnerable to
earthquakes, even in buildings that are
built to more stringent safety codes.
Earthquake related strains are imparted
to a fire protection system through the
building or the ground to which it is attached,
or through the inertial movement
within the system itself.
In a Property Loss Prevention Data
Sheet entitled “Earthquake Protection for
Water-based Fire Protection Systems,”
FM Global says that uncontrolled differential
movement can cause damage when
fire protection systems are not provided
with the necessary features that incorporate
sway bracing, flexibility, clearances
and anchorage where needed.
Significant impairments to fire protection
systems may expose a facility to a severe fire loss following an earthquake.
The most common type of damage is
water damage due to water leakage from
broken overhead sprinkler piping or sprinklers,
primarily due to lack of sway bracing
where needed.
Common sources of water damage
were broken or separated overhead sprinkler
piping, broken sprinklers due to impact
with nearby structural members or
other equipment, broken sprinklers or pipe
drops due to excessive differential movement
between unbraced suspended ceilings
and the pipe drops, and broken inrack
sprinkler system piping or sprinklers
due to excessive rack movement.
In addition to damage from water leakage,
fire protection systems are often impaired
due to direct damage to the systems,
or due to damage to public water supplies
or utilities needed for fire protection.
In evaluating the many incidents of
damage, FM Global says two conclusions
are very apparent:
1. Only by providing in a systematic
manner the necessary features, which
incorporate sway bracing, flexibility,
clearances and anchorage where
needed, can a fire protection system be
adequately protected to mitigate potential
damage from earthquakes; and
2. Omission of only a few of the critical
components necessary for adequate
earthquake protection may
create conditions where significant
earthquake damage may result in substantial water damage.
The necessary shutdown of the system
to stop further damage also creates a fire
protection system impairment.
To improve the likelihood that the fire
protection systems will remain in working
condition after an earthquake, and to
minimize potential water damage from
fire protection system leakage, FM Global
recommends the following:
1. Brace piping or equipment to minimize
uncontrolled differential movement
between piping or equipment and the
structure to which it is attached;
2. Provide flexibility on piping systems and
on other equipment where differential
movement between portions of those piping
systems or equipment is expected;
3. Provide clearance between piping or
equipment and structural members,
walls, floors, or other objects so that
potential damage from impact is
minimized;
4. Provide anchorage to minimize potential
sliding and/or overturning;
5. Use appropriate types of pipe hangers
and sway bracing, properly locate them, and properly attach them to the
structure to minimize the potential
for pullout;
6. Use appropriate types of piping and
pipe joining methods to minimize
potential pipe breaks; and
7. Provide fire protection system plans
and calculations with proper verification
of design, and proper verification
that the completed installation is in accordance
with the design as well as
good installation practices.
Sway Bracing
Sway bracing for sprinkler systems,
when provided in conjunction with the
recommended flexibility will minimize
differential movement between the piping
system and the structure to which it is attached.
Flexible couplings allow sufficient
flexibility between portions of systems
where needed.
Actual design of sway bracing is based
on horizontal seismic load. For risers and
overhead sprinkler piping, there are two
sway bracing designs: two-way and fourway.
Two-way braces are either longitudinal or lateral, depending on their orientation
with the axis of the horizontal pipe.
Lateral and longitudinal braces resist differential
movement perpendicular and parallel,
respectively, to the axis of the pipe,
and are typically used on feed mains, cross
mains and system branch lines that are 2.5
in. (63 mm) and larger in diameter.
Four-way sway bracing resists differential
movement in all horizontal directions,
and is typically provided on risers. Where
lateral and longitudinal sway bracing locations
coincide, four-way bracing may be
used to satisfy design requirements for both.
Sway Brace Design
There are four steps to properly design
sway bracing:
Step 1: Lay out sway bracing locations
with respect to the sprinkler piping
and to the structural members
to which the bracing will be
attached.
Step 2: Calculate the seismic design
load requirements for each sway
bracing location.
Step 3: Select the proper sway bracing shape, angle of attachment, size
and maximum length based on
the horizontal design load
requirement.
Step 4: Select the proper method to
attach the sway bracing to the
structure and to the piping.
A four-way sway brace should be provided
on all sprinkler risers (whether single
or manifolded type) within 24 in.
(0.6 m) of the top of the riser. The use of
manifolded sway bracing at the top of
multiple adjacent risers requires careful
design work and should be avoided. If
used, no more than two risers should be
used in a manifolded arrangement, and
bracing should be designed to carry the
total loads for both risers.
Intermediate four-way sway bracing
should be provided at an interval not to
exceed 40 ft. (12.2 m). Where flexible
couplings are used, four-way sway bracing
should be provided within 2 ft. (0.6
m) of every other flexible coupling (with
no more than two flexible couplings between
sway brace locations).
A two-way lateral sway brace should be provided within 2 ft. (0.6 m) of the end
of any horizontal manifold piping longer
than 6 ft. (1.8 m), or when there is one or
more flexible coupling(s) on either the
horizontal manifold piping or on the riser
stub between the floor and the connection
to the horizontal manifold piping.
Vertical cross main or feed main piping:
Four-way sway bracing should be provided
at both the top and bottom of the vertical
pipe run of 6 ft. (1.8 m) or more. Each brace
should be located within 24 in. (0.6 m) of
the respective piping turn. Intermediate
four-way sway bracing should be provided
similar to risers as recommended above.
For vertical pipe runs of less than 6 ft.
(1.8 m) without bracing provided, flexible
couplings should not be present within the
vertical pipe run (including the piping turns).
If flexible couplings are provided at one or
both turns for vertical pipe runs of less than
6 ft. (1.8 m), then four-way bracing should
be provided within 24 in. (0.6 m) of each
turn equipped with flexible coupling(s).
Horizontal changes of direction: Cross
main or feed main piping that has pipe
runs of 6 ft. (1.8 m) or more adjacent to the change in direction should be provided
with both lateral and longitudinal sway
bracing at the change of direction.
Ends of feed mains and cross mains:
Provide lateral bracing within 6ft. (1.8 m)
of the end, and provide longitudinal bracing
within 40ft. (12.2 m) of the end. When
structural member locations for lateral
sway bracing attachment are such that this
6ft (1.8 m) distance cannot be met, the
cross main or feed main should be extended
to allow proper location of the lateral
sway bracing.
Seismic separation assemblies in feed
mains and cross mains shall be considered
as the end of the piping on both sides of
the assembly.
For branch lines 2.5 in. (64 mm) or larger
that need sway bracing, the first lateral sway
bracing location should be no closer than
20 ft. (6.1 m) nor greater than 40 ft. (12.2
m) from the branch line connection to the
cross main. FSM
For more on this topic or other Property
loss prevention methods, go to www.fmglobal.
com/fmglobalregistration/default.asp
x?action=newcut for art as well.